Categories
News Overhaul Update Overhaul Update

January 2022 Update

Work continues on Sir Lamiel. We have made some good progress on cleaning down the inside of the frames, and we’ve now started the noisy phase. The needle gunners, Mike and I, have been hard at work and the pit at Loughborough is now filling with red paint chips. Once all the paint is removed, we will then mechanically wire brush the frames and apply some new paint.

Alan needle gunning the between the frames of 777

On the tender, work has continued on removing the brake gear in preparation for the lift. The heavy lifting gang, Jim and John, were in at the weekend to remove the vacuum cylinder bracket and the front steps. The tender is now virtually ready to lift as soon as the jacks are available.

We’re making some great progress already this year. We’ve also had the boiler inspector examine the boiler. The good news is that we had already identified and planned to do all the required repairs the inspector has identified. This means that our work schedule is not affected by additional boiler work. We can now make plans to buy the materials required to do the work.

We’ve also carried on fitting out our containers with racking so that we can store components. There are volunteers working most weekends now, as well as Mike and I doing a couple of days a month in the week. There’s plenty to do now that the boiler, frames and tender have been separated.

The shed shop is also being modernised with improved electrics and shelving. We’re aiming to get the shop open at least once per month.

Our new shed shop open during the bitterly cold Eastern Weekend

If you’re interested in getting involved, please contact comms@5305la.org.uk We want to involve as many members as possible to help us get Sir Lamiel back in steam. Even if you can only have a few hours a month to open the shed shop, it will be really useful.

As I’ve mentioned repeatedly, the challenge of fundraising remains. The news from the boiler inspector is very welcome. However, the cost of the copper bar for the replacement stays and new tubes etc will not be cheap. Orders will need to be placed soon if we are to meet our target of 2024.  There are a few ways you can help us. If you haven’t already you can  :-

Please help us to complete Sir Lamiel’s overhaul in any way you can.

Thanks for your support

Alan Berck-May

Chairman